Karré 23

Project status
Completed

Mobile vacuum system for 160 flats.

Karré 23 was the first site where screw tanks were placed in large plastic tubes and then dug under ground.

By using plastic tubes instead of concrete bunkers Envac drastically reduced the cost of installing this mobile system and made it much more time efficient.

Design inlets give the system a beautiful finish.

Basic project information
CountryDenmark
CityFredriksberg
System in operation2009
Project completed2009
Basic system data
Type of systemMobile Vacuum System
System subtypeMVS 362
Application areasResidential area
Final capacity per day3.000 litres per day
Number of fractions1
Number of inlets6
Number of tanks2
Total metres of pipe70
Type of wasteGeneral waste / Rest